Contact Us
Contact Us
Skip to content Skip to footer

200-Ton Commercial HVAC Replacement in Irving, TX

TrueServ Mechanical completed a 200-ton commercial HVAC replacement in Irving, TX, installing two Carrier 100-ton split HVAC systems at a commercial office building. Selected by Carrier Commercial Services, TrueServ managed equipment removal, installation, refrigerant piping, ductwork, electrical connections, and coordination with Carrier’s start-up and commissioning process.

Project Details

FACILITY TYPE     

Commercial Office Building

PROJECT TYPE

HVAC Replacement & Installation

EQUIPMENT

Two Carrier 100-Ton Split Systems

LOCATION

Irving, TX

INSTALLED CAPACITY

200 Tons

PROJECT COMPLETION

August 2026

Rooftop commercial HVAC unit with open electrical control cabinet during a 200-ton HVAC replacement project in Irving, TX.
Condensing Unit: Electrical & Controls Cabinet

Project Overview

Commercial HVAC Replacement for an Irving Office Building

TrueServ Mechanical was selected by Carrier Commercial Services to replace two existing 100-ton split HVAC systems at a commercial office building in Irving, Texas.

Carrier supplied the primary equipment, while TrueServ managed the removal of existing systems, crane coordination, installation, refrigerant piping, ductwork, and electrical and controls connections.

TrueServ also supported Carrier during system start-up and commissioning.

Project Highlights

TrueServ Mechanical managed the following installation activities for the commercial HVAC replacement project:

Carrier Start-Up: System Testing & Commissioning
Carrier Start-Up: System Testing & Commissioning
  • Removed two existing 100-ton split HVAC systems, including air handlers and condensing units.

  • Recovered and processed existing refrigerant.

  • Coordinated crane staging, equipment removal, and placement.

  • Installed two Carrier 100-ton air handlers and two matching condensing units.

  • Installed curb adapters and fabricated new supply ductwork and damper assemblies.

  • Installed refrigerant piping, valves, filter-drier canisters, and aluminum-jacketed insulation.

  • Replaced electrical disconnects and completed electrical and controls interconnections.

  • Supported Carrier Commercial Services during system start-up and commissioning.

More Project Photos

100 ton air handler. Completed installation.
Completed rooftop installation of a Carrier 100-ton air-handling unit
commercial office building
Office Building Exterior
HVAC ductwork
Installed refrigerant piping, valves, and aluminum-jacketed insulation

Are You Planning a Commercial HVAC Replacement?

From equipment upgrades to large-scale system replacements, TrueServ Mechanical provides commercial HVAC installation services throughout Dallas-Fort Worth. Let’s discuss your project requirements and how our team can help.